If you have only two paths through a project network diagram where path 1 has a length of 20 weeks and path 2 has a length of 30 weeks, what is the estimated duration of the project?
a. There is not enough information to answer
b. 25 weeks
c. 20 weeks
d. 30 weeks

Respuesta :

Otras preguntas

how many 1/3 and 3/4 of 20
What is deffusion and give me an example
Events A and B are mutually exclusive. Suppose event A occurs with probability .33 and event B occurs with probability .38. Compute the probability that A occu
What pieces of equipment are needed to calculate the velocity of a falling object? A; stopwatch and balance B: speedometer and magnet C: compass and tape measur
Are Husky German Shepherd mix good dogs? I know about huskies. I've been around huskies. I'm currently looking for a dog for my family. The kind that would be a
how much fats do canadians consume
What does 6 T=-------------lb
Six Ways that human-rights violations influences individuals
How many eggs does a chicken lay per day? I am starting an allotment with my uncle. He claims that a vet has been giving him information about keeping chickens,
If Thomas can travel 12 miles in one hour how many miles does he travel in 48 minutes