The most detailed element in the hierarchical breakdown of the project work to be accomplished is known as the __________.

a. deliverable
b. sundeliverable
c. workpackage
d. lowest sub deliverable
e. cost account

Respuesta :

Otras preguntas

How do you write 0.334 in expanded form?
Which of the following is an example of the correlation of productivity and a positive attitude?     A. James likes chatting with his coworkers but is easily d
thermsosphere height
how many 1/3 are in one cup
Mark wants to hang four rectangular pictures in a row on a wall so that the horizontal space between each picture is always the same. Each picture has a length
if you know that a nation uses a parliamentary system of government but have no other information what do you know for certain about the structure of that gover
what complementary colors does Paul Gauguin use in la orana maria
What is an antonym for plot
the crucible also conveys millers view on
round 64569 to thousand