  • Mathematics
contestada

The government estimates 840,000 for equipment, 15,000 for software, and 40,000 per month for wages when the project will take 16 months.

Respuesta :

andromache andromache
  • 19-02-2021

Answer:

the total cost is $1,495,000

Step-by-step explanation:

The computation of the total cost is shown below:

Let us assume the months be m

Now the equation would be

= Equipment + software + wages

= $840,000 + $15,000 + 40,000m

= $840,000 + $15,000 + $40,000 (16)

= $840,000 + $15,000 + $640,000

= $1,495,000

Hence, the total cost is $1,495,000

Answer Link

Otras preguntas

James works in a flower shop. He will put 36 tulips in vases. He must use the same number of tulips in each vase. How many tulips could be in each vase?
A muffin recipe calls for 2/5 tablespoons of vanilla extract to make 6 muffins. Arthur is making 18 muffins How much vanilla extract does he need?
What is 5,624 divided by 46
in the question do thin liquids freeze faster than thick liquids what would the independent and dependent variables be?
Write a ratio for the following word phrase. Write fractions in lowest terms.42 in. to 6 ft
What's the answer to 11d+10=6d
Why were the Intolerable Acts passed?
What number has factors that add up to thirty
What's the answer to 11d+10=6d
6-b=5b+30 how do I solve this