8. Four Men working together can finish a house repair job in 12 days.
How many days will 6 men working at the same rate finish the same ja
9 Which of the​

Respuesta :

asmaNasr
asmaNasr asmaNasr
  • 21-02-2021

Step-by-step explanation:

if 4 men did the job in 12 days , then each of the 4 men worked for 12 days , which means they worked for 4*12=48 days , so the job takes 48 work days to complete. If all men work at the same rate, then these other 6 will complete the job in

[tex] \frac{48}{6} = 8 \frac{days}{man} [/tex]

Therefore, it’ll take the group of 6 men 8 days to complete the job.

Answer Link

Otras preguntas

Find an equation of the line that is perpendicular to the graph of 2x+5y=5 and contains the point of intersection of the graphs of y=x+4 and y–2x=5. pls help me
The shoguns worked to modernize Japan’s __________.
Health effects of stress can result in all of the following EXCEPT:
who has the power to begin the impeachment process against a U.S. official?
Don't understand this?
any questions 1-4 please help me
a linear function in the form y=mx+b for the line passing through (4.5, - 4.25) with y intercept 2.5
Don't know how to do it please help
Need help with this work sheet
The number p is 20 more than the number q using algebra write the relationship between P and q