If it takes 3 days for 10 workers to finish building one house, how many days will it take 15 workers to finish 4 houses?

Respuesta :

sirinda
sirinda sirinda
  • 19-10-2017
a = house
3 days x 10 worker = a
a = 30 work unit
4a = 120 work unit
120 work unit = 15 workers * y days
y = 120/15 = 8 days

i hope this isn't too confusing 
Answer Link

Otras preguntas

Should Canada have control over its water supply
is a octopus a wet spider
Which verb form correctly completes this sentence? Yo ___ ir al cine, pero tengo que hacer las tareas. A. Desea B. Deseas C. Deseo D. Desean
A person that drinks alcohol every night but does not think they have a problem, is in what stage of change?
ΔABC is an equilateral triangle. m∠A = (3x - 12)°. Solve for x. A) 14 B) 19 C) 20 D) 24
Yeast can reproduce by__,which is when daughter cells arise as an outgrowth of the parent cell.
steps to solve A=1/2b•h
I need to answer it
Move the arrows up and down to arrange the following types of attractions between molecules in order from strongest (on top) to weakest (bottom): (2 points) Mo
Where were the first Spanish colonies located in the New World?